Topping-out ceremony Munich Freiham

sharingarrow_drop_down

GWG München Richtfest

On 18 October 2019 the topping-out ceremony for 2019 apartments was held in Munich Freiham Nord.

The IGP team of the project was almost completely represented and the topping-out wreath was pulled up in wonderful autumn weather. This was not the only feat of strength in the project. The original completion date for Building 5 was at the end of February 2020, but for political reasons the first occupation of Building 5 should take place this year.

The schedules were adjusted with great commitment and massive acceleration measures were developed for Building 5. Much to the delight of the client and the new tenants, the IGP team made it possible to move into 28 apartments in December.