Visible construction progress with ProSiebenSat.1

sharingarrow_drop_down

Baustellenansicht von oben - ProSiebenSat1 - IGP

The carcass work in the 1st construction phase is progressing rapidly here.

On the technical floor in the 2nd basement, most of the slab areas have already been concreted. And after the rising walls were completed in all areas, the water drainage could be switched off. The outer walls were sealed, the areas filled in and the cleanliness layer was placed. In other areas, the floor slab for the 1st basement level has already been concreted, some of which is around 2.0 m thick. With a public holiday break of 2 weeks, the further structural work will start again on 07.01.

Baustellenansicht von oben - ProSiebenSat1 - IGP